Approve Tab Workings

Approve Tab

What is the importance of the Approve tab in the Permit to Work (PTW), in OHS Online?

This is a really important question! Like previous mandatory sections of the PTW, this section is another fundamental section of the PTW. This is where the details of the PTW are confirmed and agreed by both the contractor (Permit Requester) and the client (Permit Issuer). The tab forms two sections, the Declaration and Approval Section (section 15) and the Hand-back and Acceptance sect View Full Answer

    Approve Tab

    How do I use the Declaration and Approval section in the Approve tab, in OHS Online?

    Great! Let's take a closer look at this section. This section must be checked and completed once the Permit Requester (contractor) has implemented all the required safety precautions as per the requirements of each tab aspect of the PTW. This part will display the relevant sections of the PTW tabs which are applicable in the PTW, providing reference back through the PTW and allowing the View Full Answer

      Approve Tab

      In OHS Online, how do I complete the Declaration of Controls section in the Declaration and Approval section of the Approve tab?

      Okay great, so you've performed checks with the contractor and you're happy all the controls are in place! Once the Permit Issuer and Permit Requester have agreed that all the necessary controls are in place, they formally sign to this fact in the declaration of controls section. This section consists of two declaration statements and a signing process: View Full Answer

        Approve Tab

        In OHS Online, how do I complete the Site Hand-back section in the Hand-back and Acceptance section of the Approve tab?

        Ah yes! Now we're down to the last section of the PTW and then we're done! This is a very important section because it's where the Permit Requester and Permit Issuer make final checks that any requirements from the safety precaution controls have been met. These controls need to be checked as YES in order to make sure they are checked and confirmed: View Full Answer

          Approve Tab

          In OHS Online, how do I complete the Hand-back Confirmation and Final Approval section in the Hand-back and Acceptance section of the Approve tab?

          Aha, we're just about done! Now for the final part of the PTW, signing it off and completing it! This section is very important because it is where the Permit Requester and Permit Issuer agree that the contractor work is now complete and that the contractor has handed the work area in question back in its original form with no detrimental effects to the client environment or infrastruct View Full Answer